Removal and replacement of 46,000’ of mainline ballasted wood tie track. Excavate 15,000 CY of old ballast and replace with new ballast. Install sign foundations and precast duct banks. Install 23,000’ of 3rd rail. Construct a new yard for Clifton Shops entailing 5,000’ of new track, 1 crossover, and 5 NYCTA turnouts. The majority of the work took place during high intensity construction weekends.
SIRT – Mainline Track Rehabilitation of Staten Island
Metropolitan Transportation Authority
$87,820,000.00
November 2023